TECHNICAL SPECIFICATIONS · DIVISION 07
07 13 00 · Waterproofing
- Project
- San Martín Education Center · LPN-014/2026
- Process
- Spec 07 13 00 Waterproofing.pdf
- Document
- 07 13 00 · Waterproofing
- Reference
- Section 3.2 · Execution
PART 3 · EXECUTION
3.1 EXAMINATION — Verify that substrates are sound, clean, dry, and free of irregularities that could damage the membrane.
3.2 INSTALLATION — Install waterproofing at interfaces with enclosures, parapets, and penetrations indicated in the architectural drawings.
Install a compatible SBS membrane and maintain a minimum vertical upturn of 200 mm above finished level.
Coordinate terminations with facade details. Seal exposed edges and verify adhesion before concealing the system.
Related clauses
- 3.3 PROTECTION — Protect completed membrane from traffic, punctures, and exposure before installing adjacent finishes.
- 3.4 UNFORESEEN CONDITIONS — Submit any undefined condition or conflict with the contract documents to the designer for review before proceeding.