Emerging risks · August 3, 2026 cutoff
AHU-03 is no longer only an overdue submittal: with a 14-week fabrication lead time and a September 28 on-site need, the June 22 approval date is now more than six weeks overdue. The team should evaluate an alternate and protect contractual notice.
| Signal | Source | Impact | Owner | Action |
|---|---|---|---|---|
| AHU-03 remains unapproved across three weekly cutoffs | OAC 21–23 + SUB-HVAC-031 1 | Approval due Jun 22; now more than 6 weeks overdue | PM / Design | Select alternate by Aug 7 |
| Level 03 ceiling release depends on equipment supports and penetrations | Lookahead W27–W32, act. M-318 2 | May shift ceiling close-in and overhead testing on level 03 | Field / MEP | Resequence east zone |
| The delay may trigger the seven-day impact-notice provision | Contract cl. 8.3 + OAC 23 3 | Schedule reservation may be lost if it is not documented | Contracts | Issue preventive notice |