OAC MEETING MINUTES NO. 18
OAC Meeting Minutes No. 18
- Project
- Execution change review
- Process
- OAC Meeting Notes 18.docx
- Document
- OAC Meeting Minutes No. 18
- Reference
- Item 4.3 · access, logistics, and sequencing
4 · ACCESS, LOGISTICS, AND SEQUENCING
Date: May 21, 2026 · Location: Site office · Attendees: Owner, supervision, general contractor, and facade subcontractor.
4.3 The owner advised that access through the north gate will be restricted from 6:00 p.m. to 6:00 a.m. beginning Monday, May 25.
Access through the north gate will be restricted from 6:00 p.m. to 6:00 a.m. beginning Monday, May 25.
The contractor noted that the facade crew uses this access for material hoisting and requested confirmation of an alternate route.
Related clauses
- ACTION 4.3.1 — The contractor will submit a preliminary cost and schedule impact within five calendar days.
- STATUS — The instruction is recorded without agreement on responsibility, cost, or time extension.
- 4.4 The owner will confirm the alternate facade-delivery route before May 22.
- 4.5 The contractor will keep daily records of access, standby hours, and affected resources.